Incinerator closed after dioxin breach

http://www.mrw.co.uk/news/incinerator-closed-after-dioxin-breach/8639626.article?blocktitle=Latest-news—recycling-and-waste-management&contentID=2182

Incinerator closed after dioxin breach

4 December 2012 | By Neil Roberts

A waste incinerator in South Wales has been shut down and an Environment Agency investigation launched after the facility was found to have breached emission limits for the second time. The Materials Recovery and Energy Centre at Crymlyn Burrows, Swansea was found by EA officers to have exceeded the limits set out in environmental permits for dioxin emissions. Steve Brown, area manager for EA Wales said: “Environmental permits are there to make sure that local people and the environment are protected from the impact of sites like these. “They have strict conditions and emission controls which we will enforce. The operator is complying fully with our investigation. “We will make sure they do all that they can to rectify this problem as a matter of urgency and we will consider taking further action if it is appropriate.”
The facility, which processes household waste from Neath Port Talbot and Bridgend councils, was previously shut down for breaching emission limits and accepted a caution from the EA in 2011. It has been dogged by legal wrangling and controversy since it opened in 2002 with residents’ complaints about odours, and fires at the facility in 2003 and 2010. Huw Brunt from the Public Health Wales said: “Raised levels of dioxin emissions over a short time period are unlikely to pose an appreciable health risk to the local population.”

“However, a number of breaches of the dioxin emission limit have been reported at this site over the past couple of years. This recurring problem raises associated public health concerns and we would like to see this situation resolved as soon as possible.”

EA said it was continuing its investigations at the site and would consider if further action should be taken.

The operators Neath Port Talbot Recycling Ltd, owned by Neath Port Talbot Council have begun cleaning a section of the plant which could be the cause of the breach. EA said energy-from-waste operations at the site will not resume until the company can demonstrate it is in compliance with its permit. Other operations at the facility are continuing. Will Watson, director at Neath Port Talbot Recycling, told MRW there had been three recent test results showing elevated levels of dioxins. “We think we have identified the cause and we think we have a solution”, he said. “We have begun specialist chemical cleaning of a section of duct between the bag house and the stack.”

He said if the cleaning solved the problem and the next test results were ok, the plant would be up and running after Christmas and the cleaning process would be carried out twice as often in future. But if the next test results show continuing elevated dioxin levels he said “we’ll have to have a more fundamental rethink about the waste-to-energy operation”.

Dioxin breaches halt Crymlyn Burrows waste plant

http://www.bbc.co.uk/news/uk-wales-south-west-wales-20596856

4 December 2012 Last updated at 15:14 GMT

Crymlyn Burrows

The Crymlyn Burrows waste incinerator opened in 2002

Related Stories

A £32m waste incinerator has agreed to stop operations after two breaches of its dioxins emissions limit.

Environment Agency Wales said it has launched an investigation into the breaches at the Crymlyn Burrows site in Neath Port Talbot.

Cleaning of a section of the plant, owned by the local council, is being carried out.

In August last year the plant accepted a formal caution from the agency after emission breaches in 2010.

The agency said a stricter monitoring regime was in place following those incidents and the plant was cooperating fully with the new investigation.

Dioxins are toxins formed by industrial processes and waste burning. They have been shown to contribute to higher cancer rates and to affect pregnant women.

Steve Brown, area manager for Environment Agency Wales said: “Environmental permits are there to make sure that local people and the environment are protected from the impact of sites like these.

Continue reading the main story

“Start Quote

A number of breaches of the dioxin emission limit have been reported at this site over the past couple of years”

End Quote Huw Brunt Public Health Wales

“They have strict conditions and emission controls which we will enforce. The operator is complying fully with our investigation.

“We will make sure they do all that they can to rectify this problem as a matter of urgency and we will consider taking further action if it is appropriate.”

Huw Brunt from the Public Health Wales said: “Raised levels of dioxin emissions over a short time period are unlikely to pose an appreciable health risk to the local population.

“However, a number of breaches of the dioxin emission limit have been reported at this site over the past couple of years.

“This recurring problem raises associated public health concerns and we would like to see this situation resolved as soon as possible.”

The plant, which opened in 2002, processes household waste for recycling and incineration from Neath Port Talbot and Bridgend.

It is operated by Neath Port Talbot (Recycling) Ltd – a wholly-owned subsidiary of Neath Port Talbot council.

More on This Story

Related Stories

09 JUNE 2011, SOUTH WEST WALES

24 DECEMBER 2010, SOUTH WEST WALES

From other news sites

  • Environment Agency   Agency investigates incinerator permit breaches 5 hrs ago
  • Agency investigates incinerator permit breaches
  • 04-Dec-2012
  • Officers from Environment Agency Wales have launched an investigation after an incinerator breached strict emission limits set out in its environmental permit.
  • Test results from the Materials Recovery and Energy Centre at Crymlyn Burrows, Swansea, have indicated that the site has exceeded the permitted limit for dioxin emissions on two occasions.

    The operator is co-operating fully with the Agency and has stopped all operations until the cause of the breaches can be established.

    The operators accepted a formal caution from the Agency last year following emission breaches from the site in 2010. A stricter monitoring regime is in place following those incidents.

    The operator has already started cleaning work on a section of the plant as this could be the cause of the breach.

    Dioxins are produced by fires, including bonfires and car exhausts, which can have an impact on people’s health if they enter the food chain.

    Steve Brown, Area Manager for Environment Agency Wales said:

    “Environmental permits are there to make sure that local people and the environment are protected from the impact of sites like these.

    “They have strict conditions and emission controls which we will enforce. The operator is complying fully with our investigation.

    “We will make sure they do all that they can to rectify this problem as a matter of urgency and we will consider taking further action if it is appropriate.”

    Huw Brunt from the Public Health Wales said:

    “Raised levels of dioxin emissions over a short time period are unlikely to pose an appreciable health risk to the local population.

    “However, a number of breaches of the dioxin emission limit have been reported at this site over the past couple of years.

    “This recurring problem raises associated public health concerns and we would like to see this situation resolved as soon as possible.”

    Environment Agency Wales is continuing to investigate and collect evidence and consider if further action should be taken against the operators of the site.

    The incinerator will not start routinely operating again until the company can demonstrate it is in compliance with its permit.

  • This Is South Wales    Environment Agency Wales investigates Crymlyn Burrows incinerator… 11 hrs ago

Detroit Incinerator

http://www.greatmichigan.org/additional-priorities/air/detroit-incinerator

Description: http://www.greatmichigan.org/../../sites/default/files/imagecache/220-half-column/images/kids%20covering%20mouth_cropped.jpg

While other cities and counties struggle to reduce landfill waste through recycling programs, Detroit still burns its garbage — and the garbage of its neighbors — within blocks of residential neighborhoods. For the last 20 years, the Detroit Incinerator, also know as the Greater Detroit Resource Recovery Facility, has cost the city an estimated 1.2 billion dollars, and continues to increase air pollution levels throughout the city. These pollution levels persistently exceed National Ambient Air Quality standards, and consequently contribute to the rising rates of asthma. Detroiters are three times as likely to be hospitalized for asthma compared to Michigan as a whole, and asthma death rates in Detroit are two times that for the state.

As the largest incinerator in the world, it is grossly over sized and imports garbage from nearby towns just so it can operate at design capacity. During the past several years of the City’s bond obligation for the incinerator, private haulers were charged as little as $13 per ton, while Detroit residents effectively paid $150 per ton or more. Since the Facility needed the trash to keep it burning, its served as a disincentive to recycling.

While the financial costs and health burdens remains high, Detroit continues to operate the incinerator and ignore the savings that recycling and recovery programs throughout the city would create.

Some claim the incinerator is an important feature to providing renewable energy to Detroit buildings because the burned municipal waste is converted to steam and sold to the steam loop owned by Detroit Renewable Energy. However, Detroit Thermal can, and has met all the current demands of their customers without the input from the incinerator.

Within the last five years the prospect of closing the incinerator has come close. In 2008 the City Council stated visions to adapt a new business model for Detroit solid waste and provided budget money to begin a curbside recycling program. The City’s financial obligation to the Facility ended in July 2009. In late 2010 new owners, Atlas Holdings/Detroit Renewable Energy, received a contract for burning the City’s municipal trash until 2011, but without any tonnage obligation.

Currently, organizations across Southeast Michigan are asking state legislators to create good policy to protect Detroiters. These policies include incentivizing recycling programs throughout the city and discontinue defining trash burning as a source of renewable energy. The benefits of recycling far outweigh the costs of incineration. Recycling saves natural resources, energy, landfill space and money, creates less air and water pollution, and decreases the risk of asthma related illnesses. Transitioning Detroit toward an intensive recycling program will not only save the city money, but improve the health of Detroiters as well.

ENVIRONMENT   http://www.theglobeandmail.com/news/british-columbia/toxic-ash-testing-clouds-incinerator-plans/article5032738/

Toxic-ash testing clouds incinerator plans

JUSTINE HUNTER

VICTORIA — The Globe and Mail (includes correction)

Published Wednesday, Nov. 07 2012, 6:39 AM EST

The chair of the Fraser Valley Regional District says B.C.’s environment minister Terry Lake is being “cavalier” about the risks of a carcinogenic substance, cadmium, that was recently found in 1,800 tonnes of ash transported to the Cache Creek landfill.

Chilliwack Mayor Sharon Gaetz, whose community is upwind of the Burnaby incinerator that generated that ash, is also challenging her Metro Vancouver neighbours to abandon plans for a second garbage incineration plant, saying the mishandling of toxic ash from the region’s existing facility is scary enough to warrant a different approach to waste management.

“In the Fraser Valley, we already have the highest rates of respiratory illness in the province. We don’t want to breathe these fumes.”

Testing at the landfill revealed the ash, brought from the Burnaby incinerator in July and August, could leach cadmium approaching levels at least twice the province’s acceptable limits.

“The minister says there is no harm to the environment and to the public. Cadmium causes lung cancer. To be cavalier about this issue is a black mark against the minister of environment and Metro Vancouver,” Ms. Gaetz said. “It’s about the risk and uncertainty. We don’t think it’s a green waste management option.”

Mr. Lake, in an interview Tuesday, said his ministry is investigating to find out if the ash from the Burnaby incinerator is hazardous, and if so how it was shipped to Cache Creek in contravention of the rules. As well, investigators will sample ash that has been shipped to the landfill over the past 12 years.

If core samples by the ministry confirm it is hazardous, it will have to be dug out and moved to a facility in Alberta that is set up to handle hazardous waste.

However, Mr. Lake accused Ms. Gaetz of using the issue for political leverage in her fight against Metro Vancouver’s plans for a second incinerator. “The people in the Fraser Valley are obviously concerned about air quality but essentially, the system is working. It is taking the bad stuff out so that it wasn’t in the airshed,” he said.

Metro Vancouver’s “Zero Waste” committee has won approval from Mr. Lake for a solid-waste management plan that proposes a “waste to energy” plant. The final decision will not be made until 2014, and would have to pass an environmental assessment hearing. “I feel strongly the decisions of the environment minister should be based on science, not politics,” Mr. Lake said.

Minutes from one of the committee’s meetings, however, point to concerns that the amount of garbage to feed the new facility is less than originally forecast. Vancouver councillor Andrea Reimer said that is troubling, because there would be pressure to find more fuel for the proposed facility – instead of a focus on reducing waste.

“It’s all about the feed-the-beast argument,” she said, which goes against the City of Vancouver’s push for greater reduction and recycling of waste. “We will continue to aggressively fight pieces of the plan that would work against greater reduction of waste. In our strong opinion, a new mass burn incinerator serving this region would absolutely make it impossible for us to get to those diversion and reduction targets.”

The chair of Metro Vancouver, Port Coquitlam Mayor Greg Moore, said it is too early to say if the incident with the Burnaby ash will derail plans for a second incinerator. “We have to go through the process to find out what happened,” he said. “It’s about how we deal with it when we found something was not in compliance with the regulation.”

Mr. Moore said the proposed $450-milllion plant would not lock the region into producing more garbage. Instead, the Burnaby facility would be phased out if garbage levels are reduced over time.

Currently, Metro Vancouver produces about 1.3 million tonnes of garbage a year. Most is either shipped to Cache Creek or handled at the Vancouver landfill in Delta. About 300,000 tonnes are burned in the Burnaby incinerator.

Incinerator Study

Sent: Monday, January 30, 2012 19:05

To: ‘dynamco@netvigator.com‘; ‘chair@cleartheair.org.hk

Cc: Andrew Tristem; ‘Frances Pollitt’; ‘Kelly, Frank’; Elliott, Paul

Subject: FW: Incinerator study

Dear Mr Middleton

Thank you for your enquiry on behalf of ‘Clear The Air’ in Hong Kong.   The English Health Protection Agency announced last week that they have approved funding for a Small Area Health Statistics Unit study to investigate whether there is any potential link between municipal waste incinerators and reproductive health – see

http://www.hpa.org.uk/NewsCentre/NationalPressReleases/2012PressReleases/120124Incineratorstudystatement/

This is for a two year study starting in April 2012.  Results will be made publicly available once accepted for publication in a peer-reviewed journal.

Best wishes   Anna Hansell

(Dr) Anna Hansell  MB BChir MA MRCP MSc PhD FFPH

Clinical Senior Lecturer Assistant Director, Small Area Health Statistics Unit (SAHSU)

MRC-HPA Centre for Environment and Health  Department of Epidemiology and Biostatistics

School of Public Health Faculty of Medicine Imperial College London St Mary’s Campus, Norfolk Place  LONDON W2 1PG

Phone: +44 (0)20 7594 3344 Fax: +44 (0)20 7594 0768 Email: a.hansell@imperial.ac.uk

Small Area Health Statistics Unit, Department of Epidemiology and Public Health, Faculty of Medicine, Imperial College, London, UK

http://www.macaudailytimes.com.mo/macau/36605-cuhk-to-start-10-year-plan-on-ka-ho-residents%E2%80%99-health.html

Home | Macau | CUHK to start 10-year plan on Ka Ho residents’ health

CUHK to start 10-year plan on Ka Ho residents’ health – Macau

18/06/2012 10:05:00

The government has commissioned the Chinese University of Hong Kong for a 10-year study of health conditions of the residents in Ka Ho, where local people complained of illness due to the air pollution from ashes from the nearby incinerator. The Health Bureau said they had agreed with the university on the detailed procedures of the study to monitor the health conditions of residents in the area near Hac Sa. The University was quoted as saying details of the monitoring mechanism and study methodologies would be disclosed to the public next month. Preliminary arrangements require an annual report to be published, but the final conclusion will be ten years away. The Health Bureau said the study will be conducted scientifically, impartially and independently in a professional manner. The health issues were discovered early last year when hundreds of residents, many of them students and teachers in the schools there, complained of lung and respiratory problems after the contractor working the incinerator was found to have broken safety regulations by disposing of the ashes into open areas, and a large amount of them carried to residential districts by wind

Cancer mortality in towns in the vicinity of incinerators and installations for the recovery or disposal of hazardous waste (see study attached)

• Javier García-Péreza

• Pablo Fernández-Navarroa

• Adela Castellóa,

• María Felicitas López-Cimaa

• Rebeca Ramisa

• Elena Boldoa

• Gonzalo López-Abentea

http://www.sciencedirect.com/science/article/pii/S0160412012002279

Study Link

• a Cancer and Environmental Epidemiology Unit, National Center for Epidemiology, Carlos III Institute of Health, Avda. Monforte de Lemos, 5, 28029 Madrid, Spain

• b CIBER Epidemiología y Salud Pública (CIBERESP), Spain

Received 23 July 2012

Accepted 18 October 2012

Available online 13 November 2012

Abstract

Background     Waste treatment plants release toxic emissions into the environment which affect neighboring towns.

Objectives      To investigate whether there might be excess cancer mortality in towns situated in the vicinity of Spanish-based incinerators and installations for the recovery or disposal of hazardous waste, according to the different categories of industrial activity.

Methods       An ecologic study was designed to examine municipal mortality due to 33 types of cancer, across the period 1997–2006. Population exposure to pollution was estimated on the basis of distance from town of residence to pollution source. Using Besag–York–Mollié (BYM) regression models with Integrated Nested Laplace approximations for Bayesian inference, and Mixed Poisson regression models, we assessed the risk of dying from cancer in a 5-kilometer zone around installations, analyzed the effect of category of industrial activity, and conducted individual analyses within a 50-kilometer radius of each installation.

Results      Excess cancer mortality (BYM model: relative risk, 95% credible interval) was detected in the total population residing in the vicinity of these installations as a whole (1.06, 1.04–1.09), and, principally, in the vicinity of incinerators (1.09, 1.01–1.18) and scrap metal/end-of-life vehicle handling facilities, in particular (1.04, 1.00–1.09). Special mention should be made of the results for tumors of the pleura (1.71, 1.34–2.14), stomach (1.18, 1.10–1.27), liver (1.18, 1.06–1.30), kidney (1.14, 1.04–1.23), ovary (1.14, 1.05–1.23), lung (1.10, 1.05–1.15), leukemia (1.10, 1.03–1.17), colon–rectum (1.08, 1.03–1.13) and bladder (1.08, 1.01–1.16) in the vicinity of all such installations.

Conclusions   Our results support the hypothesis of a statistically significant increase in the risk of dying from cancer in towns near incinerators and installations for the recovery or disposal of hazardous waste.

______________________________

__________

Download PDF : 1-s2 0-S0160412012002279-mainIncindeaths

Mallorca: Sun & Waste!

http://www.no-burn.org/img/pic/GOB-No-volem-ser-el-femer-dEuropa-620x350.jpg

The tourists going to the island of Mallorca in Spain are invited to bring their trash along with them to burn it in the new incinerator which is successfully fighting recycling, composting and reuse.

This is the –ironic- message that the local group GOB wanted to transmit in their latest action in front of the regional parliament upon the approval of the decree to import waste to feed the burner. Sadly, the European Commission is also supporting importing waste from many km away to the island despite being a contradiction of the proximity principle and the waste hierarchy.

In the beautiful island of Mallorca one can find the best and the worst of waste management in southern Europe. On one hand some zero waste municipalities (15% of Mallorca`s population) have implemented ambitious door-to-door source separation schemes which would allow them to recycle more than 75% of the waste. On the other hand the regional government through the company TIRME created to privatise waste management had built an incinerator with the capacity to burn 300,000tn of waste which represented 75% of all the municipal solid waste generated in the island.

After an obscure and dodgy process in 2007 this already oversized burner was enlarged with an extra capacity to burn 432,000tn more. In total, Mallorca generates 542,094 tn and has an incineration capacity of 736,000tn in 2011. The biggest incinerator in southern Europe burns 84% of all municipal waste generated in the island; hence most recyclables and compostables are today incinerated. Madness.

Today in Mallorca the more you recycle the more you pay, the more you burn the cheaper it is.

There are at least three reasons why this is a bad practice of waste and resource management:

–          It contradicts the waste hierarchy: Instead of recycling targets Mallorca has incineration targets of 62% of MSW. Before recycling or reuse the first option for waste in Mallorca is incineration. Every ton of waste that is recycled instead of burned increases the fee for the citizen because the contract with the incinerator obliges to feed it during the next 30 years, if a municipality prefers to recycle or reduce waste they will have to pay for the tones that the incinerator will not receive.

–          It goes against the European Resource Efficiency Roadmap: because of the contract with the incinerator the incentives are all for burning and not for recycling. According to the Resource Efficiency Strategy by 2020 incineration should be only for what is not recyclable and compostable. In Mallorca according to the contract most recyclables and compostables are and will be burned during next 30 years.

–          It goes against the people: the citizens are already paying the highest prices in waste management in Spain to burn waste in an inefficient incinerator that doesn’t even recover the heat. At the same time modern recycling and composting plants partly financed with EU money have to be paid when not being used because waste is being sent to the incinerator.

The case of Mallorca illustrates with all cruelty how incineration –or any kind of disposal- competes with recycling and the upper levels of the hierarchy. Hence, it is unlikely that the targets set by the EU will be accomplished unless the economic and legislative drivers are changed to prioritise recycling.

There are good examples of islands in the Mediterranean which have recycling rates above northern European standards (regions in Sardinia are above 60%). Mallorca itself has municipalities such as Esporles or Puigpunyent doing an excellent job (above 70% recycling) despite the adverse legislation and local conditions. With the right legislation and political will Zero Waste is possible in Mallorca, with current conditions sustainability is a mission impossible.

The Zero Waste movement asks the European Commission to intervene to cap the incineration overcapacity in cases like the one of Mallorca when recycling is directly hijacked. The current EU legislation gives all incentives to do the wrong thing and Mallorca is a clear example of it.

Vietnam News: Living together with smoke from incinerators

VietNamNet Bridge – Black smoke spirals up through the exhaust pipe on the roof of the funeral home. The fishy smell comes from the open outlets to the surrounding areas. Local residents in Binh Duong province complain they have to live together with the smoke from incinerators.

http://english.vietnamnet.vn/fms/environment/52506/living-together-with-the-smoke-from-incinerators.html

The incinerator next to residential quarter

The Binh Duong incinerator in Tan Dong Hiep ward of Di An town of Binh Duong province handled three incineration cases on the morning of November 5. When the mourners left, the incinerator began operating, discharging black smoke through the three exhaust pipes to the sky.

“We always get suffocated with the smoke. The situation is more terrible at night than in the day,” a local resident said to reporters. “We have to have the blanket cover over the surface to prevent the smell. If not, we cannot sleep,”he said.

Meanwhile, the reporters, though wearing two protective masks, still clearly smelled the fishy odor and the bone-ash.

A broken pipe was found behind the incinerator, from which the water from the incinerator comes out directly to the environment. Reporters’ heads got dizzy just after several minutes of standing there and breathing the fish smell.

Local residents said that the waste water has been flowing from the incinerator for the last many years, which has been soaking into the earth and the water wells, thus making the water dirty unusable.

Since the local residents reported the case to the incinerator’s management board, an edge has been built to prevent the waste water from flowing to the road. As a result, the waste water has been threading its way among the tombs and then soaking into the earth.

People not only have to live with the terrible waste water, but also have to sniff the smoke from the cremation.

Waste water and smoke attack people

Nguyen Tan Hoang, whose house faces the incinerator, said that he has been living in the fishy odor and the burnt smell for the last few years already. He has to close the doors tightly after 10 pm every day to prevent the smell, wearing a protective mask when sleeping.

Especially, Hoang complained relatives and friends do not want to visit him at home because they do not want to stay in the terrible atmosphere.

Tran Van Dinh, who lives next to Hoang, said that the board of management of the incinerator always promises that they would apply necessary measures to settle the problems, but nothing has been changed.

There are some 40 households living in the Tan An residential quarter of Tan Dong Hiep ward. The local residents here joked that they can be full up with the smoke every day, no need to eat.

Nguyen Van Trieu, an old man, said that every family has 2-3 children, and most of the children suffer bronchitis regularly. He said that local residents have complained about the environment pollution since the day the incinerator began operation.

However, the incinerator’s board of management still keeps a deaf ear to the complaints, while the situation is getting worse.

Tran Quoc Tuan, Chair of the Tan Dong Hiep ward People’s Committee, said that when inspectors come, the pipes would stop generating smoke. Therefore, the provincial environment department concludes that is cannot find any problems here. Meanwhile, local people still have to live in the serious pollution.

However, Tuan said, people have vowed that they would keep struggling to protect their lives. The problem would be discussed at the upcoming meeting between the local National Assembly’s deputies and voters.

Thanh Mai

Lawyer slams government impact report on offshore incinerator

Submitted by admin on Nov 16th 2012, 12:00am

News›Hong Kong

ENVIRONMENT

Austin Chiu austin.chiu@scmp.com

It was a breach of natural justice for head of environment department to approve review that gave green light to incinerator, court told

It was unreasonable for the Environmental Protection Department director to approve an impact-assessment report made by his own department on the proposed building of a massive offshore waste incinerator, a court heard yesterday.

Barrister Hector Pun Hei made the criticism on behalf of a Cheung Chau resident, who brought a judicial review against the HK$23 billion project on Shek Kwu Chau, an island south of Lantau.

In the Court of First Instance, Pun, one of the lawyers representing 66-year-old Leung Hon-wai, said it involved a conflict of interest when the director granted the permit that allowed the proposal to go ahead.

“It is a breach of natural justice to make a person a judge in his own cause,” Pun said.

Leung is challenging decisions by the Town Planning Board and the director of the Environmental Protection Department, which cleared the way for the incinerator’s construction. He is one of four people who lodged a judicial challenge. His was selected to proceed and the other applicants will be bound by the decision.

Johnny Mok SC, for the government, rejected a criticism by Leung’s lawyers that the environmental-impact assessment report did not meet the requirements specified in a technical memorandum and a study brief from the administration.

On Wednesday, Leung’s lawyer contended that the report was substandard, because the department deferred looking at how it would remedy the permanent loss of a 31-hectare marine habitat of high ecological value. That problem was to be considered in a supplementary study.

Yesterday, Mok said that while the department was not allowed to make another environmental-impact report, a supplementary study that sought to help with the “technical implementation” of the measures must be permitted.

Mok said the environmental-impact assessment already included, as required, a study on the feasibility and effectiveness of establishing a 700-hectare marine park to make up for the loss of the existing habitat, which was home to finless porpoises.

The supplementary study would deal with the marine park’s ecological profile, extent and location.

“It would be strange if there was no further study,” Mok said. “The fact that a small corner of a vast stretch of water where finless porpoises swim is cut out doesn’t mean a massive loss. You have to consider the bigger picture.”

He also said it was wrong for the other side to suggest that the department did not conduct any studies on the establishment of the marine park, citing reports from various departments from 2002 and last year.

“This is a careful regime designed to protect the valuable species,” Mok said, referring to the creation of the marine park.

The hearing continues today before Mr Justice Au Hing-cheung.

Topics:

Incinerator

Shek Kwu Chau

Lantau

Environmental Protection Department


Source URL (retrieved on Nov 16th 2012, 5:42am): http://www.scmp.com/news/hong-kong/article/1083308/lawyer-slams-government-impact-report-offshore-incinerator

Environmental report on Shek Kwu Chau incinerator fell short, court told

Submitted by admin on Nov 15th 2012, 12:00am

News›Hong Kong

COURTS

Austin Chiu austin.chiu@scmp.com

Environmental impact report failed to meet requirements, court is told

The environmental impact report for a massive offshore waste incinerator failed to meet the requirements of a technical memorandum and a study brief from the government, a court heard yesterday.

Lawyer Valentine Yim See-tai made the assertion in the Court of First Instance as a legal challenge to the HK$23 billion project on Shek Kwu Chau, an island south of Lantau, began.

Yim is representing Leung Hon-wai, 66, a resident of nearby Cheung Chau island, in a judicial review challenging decisions by the Town Planning Board and the director of the Environmental Protection Department, which cleared the way for the incinerator’s construction.

Johnny Mok SC, for the government, said the report had met requirements.

Outside court, Leung said: “My family has been living on Cheung Chau for eight generations. We are particularly worried about the air quality and pollution likely to be caused by the incinerator. It is close to the community. We would have no objection if it was elsewhere.”

Leung is one of four people who lodged a judicial challenge to the project. His was selected to proceed and the other applicants will be bound by the decision.

Yim said that one ground for the challenge was the department’s failure to explain, as required, any measures to remedy the loss of an ecologically important 31-hectare marine habitat, home to finless porpoises.

“Our complaint is that the technical memorandum requires that the offsite mitigation measures be made during the environmental impact assessment; now they say ‘let’s deal with it in the further study’,” he said. “There should not be another report. It should have been done in the same round.”

Yim acknowledged that the government had said it would produce a study on establishing a marine park before construction began, adding that this still fell short of requirements.

The report should have included the profile and location of the proposed park, he said.

Yim said the report also failed to explain why no alternatives to an incinerator were considered and no full study of the health effects of various waste-disposal technologies conducted.

“If they discarded alternatives, they should make it clear so people would know they were discarded. If there is no proper assessment, there could be dire consequences,” Yim said.

af3f1fa278313d7005475169ef8d2e8a.jpg

Topics:

Incinerator

Shek Kwu Chau

Lantau


Source URL (retrieved on Nov 15th 2012, 6:11am): http://www.scmp.com/news/hong-kong/article/1082519/environmental-report-shek-kwu-chau-incinerator-fell-short-court-told

New milestone in burning incinerator saga

SCMP

Submitted by admin on Nov 10th 2012, 12:00am

Business

LAI SEE

Howard Winn

Exploratory vessels a new milestone in burning saga

Although government plans to build a monster incinerator in the environs of Shek Kwu Chau have officially been shelved, preparatory work continues.

Concerned citizens have noticed the presence of a number of vessels at work off the island. It turns out they are engaged in site investigation work involving the drilling of bore holes according to a Marine Department notice dated July 11, several months after the decision to shelve the project.

The assumption has always been that with the shelving of the project and the arrival of wiser heads at the Environmental Protection Department, it was doomed. The site investigation work would seem to indicate that we should not necessarily draw that conclusion.

Another possible conclusion is that the government is saying one thing and doing another. The incinerator saga reaches another interesting point this week with a judicial review of the environmental impact assessment of the project starting on Wednesday.

One argument likely to be raised is that there has been a failure of natural justice in approving the EIA because the Director of Environmental Protection acted both as the proposer and regulator of the project. Environmental groups have been pointing out this conflict of interest since the posts were merged in 2005.

It’s thought that the judicial review is likely to result in a ruling in a month or so, and whatever that may be, there is likely to be an appeal because of the significance of the issue – failure of natural justice – which will need to be resolved at a higher level.

Contact Us Have you got any stories that Lai See should know about? E-mail them to howard.winn@scmp.com

Topics:

Incinerators

Source URL (retrieved on Nov 10th 2012, 6:25am): http://www.scmp.com/business/article/1078977/new-milestone-burning-incinerator-saga

Basel changes ‘could burden’ exporters

http://www.letsrecycle.com/news/latest-news/legislation/basel-changes-2018could-burden2019-household-waste

Exporters of recovered materials from households could be subject to strict environmental requirements equal to those for hazardous wastes under proposed changes to the Basel Convention, the Bureau of International Recycling has warned.

The BIR’s environmental and technical director, Ross Bartley, told delegates at a meeting of the organisation’s International Environment Council in Barcelona last month that work is ongoing to update the Convention, which was established in 1989 by the UN to regulate the movements of hazardous wastes.

Ross Bartley, environmental and technical director, BIR

Ross Bartley, environmental and technical director, BIR

Mr Bartley is an observer to the UN’s Technical Expert Group, which has met twice to discuss the development of a framework for the environmentally sound management of hazardous waste, and is due to meet for a third time in January 2013, where final proposals are set to be agreed.

The framework will add a number of additional requirements for the export of hazardous waste which would apply to waste generators, waste carriers and operators of waste management facilities.

These include measures that would see facilities having to comply with strict emission limit values, tougher waste acceptance and handling criteria and having to undergo stringent environmental and social impact studies.

Requirements

However, in its current state, the Convention also covers waste collected from households and residues arising from the incineration of household wastes, and according to Mr Bartley, there is a danger that these types of waste could be caught up in requirements which are only necessary for hazardous waste treatment.

He explained that when the Convention was originally drafted, it was rare for waste to be segregated into different material streams and it was necessary for the regulations to apply to household waste to prevent it from being dumped overseas.

He said: “That was 30 years ago, and now those are being separated at source, and you are getting individual materials that do not need to be controlled in the same way. There is then a dilemma about how you describe what the Convention covers, as these are clearly not hazardous wastes.”

Exemption

Currently, there is no exemption in the Framework which excludes separated materials from household waste from the requirements, but Mr Bartley has lobbied to have a footnote added which would do so. However, he added that it was still not clear if this would be included in the final draft, and that some parties had opposed the changes.

He also commented that the requirements would add additional burdens for the treatment of household waste and that it could become ‘more difficult’ for exporters and handlers of waste attempting to transport material for recycling.

He added: “The burdens are according to what waste is covered and currently the Basel Convention does not have these requirements that are going to be put on governments, waste carriers and waste management facilities.

Related Links

Bureau of International Recycling

Basel Convention

“The footnote becomes quite important in that way, as otherwise the requirements would cover a plant that is recycling PET bottles for example. If you have got someone handling mercury waste you can see that there is a need, but the requirements would have to be very different for household waste.”