Lack of accountability stinks

Letters to the editor, January 11, 2016

As if the report by the [1] Audit Commission [2] on the Environmental Protection Department is not embarrassing enough (“Hong Kong’s waste problem: a stinking trail of missed targets, data errors and misdirected efforts [3]”, December 1), the Legislative Council’s Public Accounts Committee’s two hearings last month on food waste reduction and recycling will enshrine the department in perpetuity in the Hall of Shame in Mismanagement.

We learned that the department handled the growing problem of food waste, which accounts for 38 per cent of municipal solid waste in Hong Kong, in a piecemeal, disjointed manner. We learned that the department has no idea on how each programme quantitatively contributes to the reduction of food waste, which has increased by 13 per cent from 3,227 tonnes per day in 2004 to 3,648 tonnes in 2013. We learned that targets are either non-existent or not met if they’d been posted. We learned that officials are not accountable for their mistake, and the same consultant who partnered with the department in the mistake continues to advise the department on a bigger project.

After spending HK$150 million and HK$50 million to reduce food waste in schools and private housing estates respectively, the department cannot explain how much food waste was reduced as a result of those programmes. The same goes for the HK$18.7 million spent during 2013 and 2015 in advertising, marketing, and education programmes to promote the department’s signature Food Wise campaign.

Only 26 out of 1,027 business entities provided data on their efforts to reduce food waste on a voluntary basis. No data was provided by the 294 schools who signed onto the Green Lunch Charter on the result of their effort.

Phase one of the Organic Waste Treatment Facilities that was priced at HK$489 million in 2010, with the help of a consultant company which earned HK$8.8 million for its advice, turned out to cost HK$1.53 billion. The Audit Commission pointed out that essential components were underestimated in the initial estimate.

Despite clear evidence in the commission’s report showing mistake in professional judgment, Mr Elvis Au, assistant director of the department, insisted that rising cost and lack of reference price of the facilities were the causes of the cost overrun. Mr Au and the same consulting company have since moved on to manage one of the most expensive project in the department’s history – building an incinerator at Shek Kwu Chau.

Is there accountability in Hong Kong?

Tom Yam, Lantau